I am in automotive industry. our company will run MRP every Sunday and we will create schedule line release through ME84 every Monday. but I noticed one MRP run controlling parameter in the MD02, create purchase req, we always choose purchase requisition in the opening period.
My question is, every Monday, we create schedule line release and transmit to our vendor and I never found any purchase requisition in MD04. why we still need this parameter? could any experts specify the usage of this parameter? Thanks in advance.
subject edited by: Jürgen L