Dears:
This is my first question in SAP, I'm a little bit lost about where place my question... I hope I haven't been allocated in the wrong place.
I'm user of SAP PR2.
1)Sometimes we have some PO's with 6-10 items (each of them with different delivery date)
The supplier confirms delivery for the date requested in the order. How can I confirm (confirmations AB) all the lines at the same time (single batch)? I tried by using "Fast change" but it only works with "Delivery dates" (items panel).... :-(
2)If there is no way when each Item (pos 10, pos 20, pos 30) has different delivery date, is it possible when all delivery date are the same (Example: August 08th)?
3)If there is no way to do it semi-automatically, could we at least create one AB line (manually --Confirmation Category), and by clicking (Shift + F6 or something ----In Oracle it was possible....), copying the upper record and just modify the delivery date by hand (panel: Confirmations)??
4)On the other hand, we have to (sometimes) create orders copying item 10, several times, just changing delivery date, it is like an split for a whole amount. Example: 5000 units to be delivered in 5 different delivery times.
I could just release one single item for 5000 units, and after confirm (5 confirmations AB) with the amount confirmed each date, but the supplier asks us for receive the orders splitted in the first place.
Thanks in advance for your support :-)