I have a question about the project stock.
Project Stock is consider by MRP as part of available stock in standard SAP.
However, if I look at the MD04, it doesn’t seem the standard SAP take into consideration of project stock during MRP run. Please see following pictures.
A – There is a stock quantity of 115EA, and a maintenance order requirement of 300EA, and a project stock with WBS element of 120EA.
B – After a MRP is run, a planned order is generated with 185 proposal.