Hi,

 

I have a question about the project stock.

 

Project Stock is consider by MRP as part of available stock in standard SAP.

 

However, if I look at the MD04, it doesn’t seem the standard SAP take into consideration of project stock during MRP run. Please see following pictures.

 

 

A – There is a stock quantity of 115EA, and a maintenance order requirement of 300EA, and a project stock with WBS element of 120EA.

 

P1.jpg

 

B – After a MRP is run, a planned order is generated with 185 proposal.

 

P2.jpg

 

Thanks