Thank you Rajneesh
System is picking cost what was saved on 19112013
That time we have planned price 1 maintained in the system
system picked up the cost and updated
Later he deleted the planned price 1 and he put do not cost indicator
as i said user also changed the price control from S to V on 21112013
Now on 05012014 user is executing new cost estiamte
As per the system do not cost mark is there but this material is raw material
becuase price control has changed
Plan price 1 also deleted
this material is one of the component in FG
when i checked the FG cost on 05012014 for that material system still picked the cost estiamte saved on 19112013 why?
system not suppose to pickup that cost
CK40N user also selected Always recost material
Best Regards
Bhima