Thank you Rajneesh

 

System is picking cost what was saved on 19112013

That time we have planned price 1 maintained in the system

system picked up the cost and updated

Later he deleted the planned price 1 and he put do not cost indicator

as i said user also changed the price control from S to V on 21112013

Now on 05012014 user is executing new cost estiamte

As per the system do not cost mark is there but this material is raw material

becuase price control has changed

Plan price 1 also deleted

this material is one of the component in FG

when i checked the FG cost on 05012014 for that material system still picked the cost estiamte saved on 19112013 why?

system not suppose to pickup that cost

CK40N user also selected Always recost material

 