Hi Brahmankar
Sorry for late reply
As per your suggestion I have run ccr no inconsistency found in planned order no log is present in slg1
And i have run product heuristics in rrp3 But still my planned orders are having category (8)
Initally when I triggering Gatp it is calling CTP to check availabilty .In my my Planning run first step is to delete fixed pegging sap_PP_011 second step calling CTP heuristic third step is Generate fixed pegging Sap_PP_019 heuristics .
Initally some time i am getting planned order with category (5) and some time (8) .I want to know how system will decide to generate 8 th or 5 I.e whether send to external system or not
Regards
Virender