Hi Guys,
When multiple requisitions exist for the same material in the same plant, checking "Generate Schedule Lines" in ME59 ensures they are all converted to one single line on the PO.
Other items are the opposite.
The requisitions are converted into the one PO, but are spread out across multiple lines instead of generating a delivery schedule.
Are there any specific changes made to a requisition which would cause this??
I've tried changing the delivery manual to ensure the Fixed Indicator checked but it doesn't seem to make a difference.
All reqs are MRP generated