Hi
1. Kinldy check whether PR generated for the Material where the Procurement type is PR + Res for WBS element.
2. Please Make sure that the purchase requisition indicator set for the activity where the material assigned.
3. Check the below thread if the Project is valuated Project stock.
I hope that the 3rd one may resolve your issue.
Thanks
Ganesh