Re: How capacity requirement calculated in RCCP in SOP

$
0
0

Hi Kumar,

 

To view the source of the capacity requirements in a period, place your cursor on the period and choose Views - Capacity situation -Pegged requirements

 

Capacity Requirements:

 

Refer Note 48840 - Consulting: Scheduling during SOP planning

 

The capacity requirements for all capacities are calculated and stored via a programmed formula for a work center in the rough-cut planning profile. That is, the formulas from the work center are not considered.

Formula: For each period from the rough-cut planning profile

Capacity requirements = Work * quantity / base quantity

Explanation:

Work = Capacity requirements for each period in the rough-cut planning profile

Quantity = Production quantity from the SOP planning table

Base quantity = Procurement quantity, only '1' can be maintained at the moment

 

Thanks & Regards,

Ramagiri